Key dates
July 2019: Launch of the InDiD project
February 2020: Validation of the list of new InDiD use cases (in relation to the other projects supported by the MTECT), and their functional description.
2021: Launch of the main equipment contracts for the InDiD pilot sites.
June 2021: Validation of the first version of the InDiD use case specifications
June 2022: Completion of the developments planned for the InDiD use cases
October 2022: Completion of the ex-ante studies scheduled as part of the project
November2023: Completion of the cross-functional studies
Mid 2023 to mid 2024: Completion of the deployment of physical equipment on the pilot sites, as well as tests on the use cases.
May 2024: Completion of the project's final ex-post studies
11 and 12 June 2024: end of project seminar
30 June 2024: End of the InDiD project