Key Dates

2024

  • Project launch
  • Start of functional definitions of new Use Cases (UCs)

2025

  • Definition of evaluation methodologies
  • Finalization of functional definitions of new UCs
  • First production releases of mature UCs by historical partners
  • Start of technical specifications for new UCs

2026

  • Finalization of functional specifications and selection of relevant CUs for validation
  • Second wave of production releases of mature use cases by historical and new partners
  • Start of data collection for evaluations
  • 1st transnational SCALE test

2027

  • Finalization of all specifications for new CUs
  • Development of equipment prototypes and interoperability and security tests for validation
  • Third wave of production releases

2028

  • Finalization of development and validation
  • 2nd SCALE transnational test
  • Updating of CU catalog
  • Report on evaluations and impact analyses
  • Last wave of new CU production releases
  • End of SCALE project